Built to code
المعايير والجودة
We specify materials carrying at least one of these listings and design every system to the codes below. Civil Defense approval is the final check, and our documentation is prepared for it from day one.

Design codes
The codes we design to
NFPA 13
Sprinkler installation
NFPA 14
Standpipe & hose
NFPA 20
Fire pumps
NFPA 24
Private fire mains
NFPA 25
Inspection & maintenance
NFPA 2001
Clean agent systems
NFPA 12
CO₂ systems
NFPA 10
Portable extinguishers
NFPA 72
Fire alarm interface
EFC
الكود المصري لحماية المنشآت من الحريق
Where the Egyptian Fire Code and NFPA differ, we design to the stricter requirement and note it on the drawings.
Testing before handover
Every system is proven
| Test | Criteria | Reference |
|---|---|---|
| Hydrostatic test | 200 psi (13.8 bar) for 2 hours, no pressure loss | NFPA 13 |
| Underground flushing | Mains flushed before connection to risers | NFPA 24 |
| Main drain test | Static and residual pressure at each riser | NFPA 25 |
| Alarm valve trip | Flow switch, gong and panel signal per zone | NFPA 13 |
| Pump acceptance | 0%, 100% and 150% of rated flow | NFPA 20 |
| Room integrity | Door-fan test to confirm agent hold time | NFPA 2001 |
Handover package
✓ Material submittals✓ Signed test certificates✓ As-built drawings✓ O&M manuals✓ Operator training✓ Civil Defense file
Have drawings or a BOQ?